Solar Hank

How long does solar installation take?

The panels go up in a day or two. The paperwork around them takes months. Here are the real medians.

Hank, the illustrated Solar Hank character, thinking

From signing the contract to the utility's permission to operate, the median home solar project in 2024 took 93 business days, about 4 months; the middle half of projects took 64 to 150 business days. That is from NREL's SolarTRACE data on projects up to 10 kW reported by installers (NREL SolarTRACE). The installation itself is a small part of it.

Where the time goes (US, 2024 medians)

StepMedian business daysMiddle half of projects
Design: contract to first permit application209–39
Permit review by the city or county72–14
Utility pre-install review51–11
Installation work after approvals105–21
Inspection115–24
Final utility approval (permission to operate)73–14

Business days, systems up to 10 kW without a battery. Steps overlap and not every utility requires a pre-install review, so they don't add up to the total. Before installation: 63 days median; after: 28.

Permit, inspection and utility steps in the cities I cover

Median business days in the latest year with enough projects. The paperwork is quickest in San Diego and slowest in Yonkers among these cities:

CityPermit reviewUtility pre-install reviewInspectionPermission to operateData
Phoenix, AZ042582024, 158 projects
Tucson, AZ051162024, 204 projects
San Antonio, TX048112024, 84 projects
Austin, TX414102024, 39 projects
San Diego, CA00322024, 40 projects
Fresno, CA1010122023, 815 projects
Chandler, AZ14482024, 23 projects
Scottsdale, AZ44682024, 19 projects
Gilbert, AZ06392023, 83 projects
Glendale, AZ84882024, 30 projects
Tempe, AZ1461892023, 27 projects
Peoria, AZ2041682024, 30 projects
Surprise, AZ124782024, 36 projects
San Jose, CA001042024, 51 projects
Bakersfield, CA208122023, 432 projects
Clovis, CA3011122023, 289 projects
Chula Vista, CA901272023, 430 projects
Oceanside, CA101172023, 336 projects
Carlsbad, CA30672023, 178 projects
New York, NY61312024, 54 projects
Elizabeth, NJ571592023, 33 projects
Yonkers, NY7011432022, 68 projects

Same source, jurisdiction and utility with the most projects for each city. 0 means same-day approval was the median. "—" means no pre-install review or too few projects to report.

What you can do about it

Run your own numbers

Enter your ZIP and bill to see what the system will save once it's on.

Keep reading

Installer records by city: solar companies in Phoenix, solar companies in Tucson, solar companies in San Antonio, solar companies in Austin, solar companies in San Diego, solar companies in Fresno, solar companies in Chandler, solar companies in Scottsdale, solar companies in Gilbert, solar companies in Glendale, solar companies in Tempe, solar companies in Peoria, solar companies in Surprise, solar companies in San Jose, solar companies in Bakersfield, solar companies in Clovis, solar companies in Chula Vista, solar companies in Oceanside, solar companies in Carlsbad, solar companies in Toms River, solar companies in New York, solar companies in Elizabeth, solar companies in Yonkers.